Site grading must drain water while keeping routes usable. Drainage minimums depend on the surface and use; accessibility rules separately distinguish a walk at 1:20 or flatter from a ramp with a 1:12 maximum slope.

Key points

  • Drainage minimums vary by surface and use. Common planning slopes range from about 0.5% to 5% for sewers, roads, walks, lawns, swales, and paving. Use the value for the surface being designed.
  • Walking / landscaping comfort (typical max grades):
    • 2–10% — comfortable for walking and planted/lawn areas.
    • Above ~10% — starts to feel steep; may need erosion-control measures.
    • 20–40% — challenging to walk; erosion concerns depending on soil.
    • 50% and higher — difficult to hold without structural support (walls, terracing).
  • Accessible routes — the two break points:
    • ≤ 1:20 (5%): an accessible walk/route. Stays a walk, not a ramp.
    • Steeper than 1:20: counts as a ramp and must meet ramp rules.
    • 1:12 (~8.33%): the maximum running slope a ramp may have.
  • Lay out paths along contours so the running slope stays gentle and water is directed off the path — preventing puddles and ice.

Site slope thresholds pair drainage, access, and stability

ORDERED · NOT TO SCALE

Use rise over run to translate ratios and percentages, then match each threshold to its purpose

View diagram Hide diagram

Scroll horizontally to explore

Site slope notation and ordered drainage, accessibility, erosion, and structural thresholds A conventional rise-over-run triangle explains slope notation. Two blue equivalences state that one to twenty equals five percent and marks the walk-to-ramp dividing line, while one to twelve equals about 8.33 percent and marks the ramp maximum. An ordered ladder at schematic spacing places fifty percent and steeper at the top for structural support, ten percent and steeper for erosion concern, the two accessibility thresholds in blue, and a roughly half-percent to five-percent band at the bottom, because drainage minimums vary by surface. HOW SLOPE IS WRITTENRUNRISEslope = rise ÷ run1:20 = 5%walk-to-ramp threshold1:12 = 8.33%accessible ramp maximumTHRESHOLDS · STEEPEST AT TOPschematic spacing50%+Structural support requiredretaining walls or terracing10%+Erosion-control concernmeasures may be needed1:12 · 8.33%Accessible ramp maximumsteepest compliant ramp run1:20 · 5%Walk-to-ramp thresholdsteeper routes become ramps~0.5–5%Drainage minimums vary by surfaceuse the value for the surface designed
  • rise ÷ run

1:20 (5%) is the walk-to-ramp dividing line; 1:12 (8.33%) is the ramp's own maximum.

Confusions / comparison

SlopeValueWhat it means
Minimum to drainDepends on surface and useCheck the requirement for the actual condition
Comfortable walking2–10%Walks, lawns, planting
Accessible route threshold1:20 (5%)At/under = walk; over = ramp
Ramp maximum1:12 (~8.33%)Steepest compliant ramp run
Steep / structural>10%, then 50%+Erosion control; then retaining/terracing

→ Swales vs berms (this module): the grading elements that move the water · Runoff strategies (this module): steep- vs shallow-site drainage · Code: accessible ramp handrails, landings, and slope limits in detail.