← Project Management

Sheet G-106
PjMCE PcM

AIA Agreementsconcept

AIA owner-contractor documents: A101, A133, and A201 General Conditions

One-line orientation

A101 is commonly used for a stipulated-sum design-bid-build contract. A133 is commonly used for a CM-at-risk contract with cost-plus payment and a Guaranteed Maximum Price (GMP). Both use A201 General Conditions.

Key points

  • A101 — Owner-Contractor Agreement (Stipulated Sum):

    • Used in design-bid-build projects; the owner contracts directly with an architect (B101) and separately with a contractor (A101).
    • Payment is a stipulated (fixed) sum established by competitive bidding or negotiation before construction begins.
    • Progress payments are based on percentage of completed work plus stored materials; retainage is commonly set around 10% by contract/custom, but the parties define it.
    • The architect is the Initial Decision Maker (IDM) in contract disputes; the architect also certifies payment applications.
    • Aligns with the B101 owner-architect agreement; cross-references A201 for general conditions.
  • A133 — Owner-CMc Agreement (Cost-Plus with GMP):

    • Used when the contractor is a CM as Constructor (CMc), also called CM-at-risk.
    • Payment basis: cost-plus fee (owner pays actual costs), subject to a Guaranteed Maximum Price (GMP) ceiling set during the design phase.
    • The CMc is engaged early — during design — to provide cost, schedule, and constructability input; this early involvement is the defining characteristic.
    • Dispute resolution differs from A101 projects because of the CMc’s dual role during design and construction.
  • A201 — General Conditions of the Contract for Construction:

    • Not a separate agreement — it is the legal backbone incorporated by reference into both A101 and A133 (and other owner-contractor forms).
    • Defines the contract documents, roles of owner/contractor/architect, changes in the work, contract time, dispute resolution procedures, and more.
    • Bidding documents become contract documents only when the executed agreement identifies or incorporates them.
    • For sustainable projects, AIA appends E204 (Sustainable Projects Exhibit) to the A201-family agreements rather than issuing a standalone “SP” version of A201.

Owner–contractor agreements differ; A201 is the shared backbone

Same parties, same general conditions — the accent marks the one line that changes, the agreement the owner signs.

View diagram Hide diagram

Scroll horizontally to explore

Design-bid-build and CM-as-constructor owner-contractor agreements on one relationship grid Two stacked relationship panels compare design-bid-build and CM as constructor. Contract lines identify the owner-architect, owner-contractor, architect-consultant, and contractor-subcontractor agreements. A closing note explains that a bidding document becomes a contract document only when the executed agreement identifies or incorporates it. Design-bid-build — A101 stipulated sumthe contractor is bid after the documents are completeA201 General Conditions — binds owner, architect, and contractor alikeB101A101C401A401ArchitectOwnerContractorConsultant(s)SubcontractorsSuretyA310 · A312owner is the obligeeCM as constructor — A133 cost-plus with a GMPthe constructor is engaged during design, so there is no completed set to bidA201 General Conditions — the same backbone, a different agreement above itB103A133C401A401ArchitectOwnerCMcthe contractor · GMPConsultant(s)SubcontractorsA bidding document becomes a contract document only when the executed agreement identifies or incorporates it.

Document numbers are drawn without year suffixes; the numbers are stable, the editions are not.

Confusions / comparison

A101A133
Agreement typeOwner-Contractor (DBB)Owner-CMc (CM-at-risk)
Payment basisStipulated sum (fixed)Cost-plus fee with GMP ceiling
When contractor engagedAfter design (via bid)During design (early involvement)
Typical delivery methodDesign-bid-buildCMc / CM-at-risk
Architect’s IDM roleYes — architect is Initial Decision MakerModified — CMc’s presence changes dispute process
Paired general conditionsA201A201 (same backbone)
DocumentWhat it isRole in the contract
A101Agreement form — payment terms, schedule, contract sumBinds owner to contractor; sets the money and time deal
A133Agreement form — cost-plus/GMP terms, CMc scopeSame purpose as A101 but for CMc delivery
A201General Conditions — rules of constructionLegal framework referenced by both A101 and A133; not duplicated in either

→ AIA documents by delivery method (this module): how A101/A133 map to each delivery method · AIA G-series forms (this module): the administrative forms used during construction under A201 · Owner-architect agreement B101 (same topic): the counterpart agreement that pairs with A101 in DBB.