← Project Management

Sheet G-136
PjMCE PcM

Project Deliveryconcept

Owner-contractor payment structures: stipulated sum, cost-plus, GMP, unit price

One-line orientation

The owner-contractor payment structure determines who absorbs cost risk — the contractor or the owner — and understanding each type is essential for both PjM project-delivery questions and CE contract-administration questions.

Key points

  • Stipulated sum (lump sum) — AIA A101:
    • Contractor agrees to complete the work for a single fixed amount.
    • Contractor bears the risk — if actual costs exceed the sum, it comes out of the contractor’s profit.
    • Owner benefits from cost certainty; requires a fully designed project before contract is signed.
    • Alternates, allowances, and unit prices can be embedded within a stipulated sum contract to handle known unknowns.
  • Cost-plus-fee:
    • Owner pays the contractor’s actual cost of work plus an agreed fee (fixed fee, percentage, or other).
    • Owner bears the risk — no ceiling on total cost.
    • Requires open-book accounting and owner trust; appropriate when scope cannot be fully defined.
  • Guaranteed Maximum Price (GMP) — AIA A133 with CMc:
    • A GMP is a cost-plus contract with a cap on the agreed scope and cost basis. Approved contract changes may adjust the cap.
    • Savings below the GMP go to the owner unless the contract expressly provides a sharing formula.
    • GMP is established based on design documents available at the time — includes allowances for incomplete scope.
    • Pre-GMP estimates by the CMc are not guaranteed; the GMP itself is the binding ceiling.
    • Commonly used with the Construction Manager as Constructor (CMc) delivery method.
  • Unit prices:
    • Used when the quantity of work cannot be determined in advance (earthwork, piling, demolition of unknown extent).
    • A price per unit is agreed; the total payment adjusts based on actual quantities.
    • Often embedded within a stipulated sum or GMP contract for specific line items.
  • Retainage: the owner withholds part of each progress payment as an incentive to finish the work. The agreement and applicable law control the percentage and release date; retainage may remain until Final Completion.

Who bears the cost-overrun risk

Overrun risk shifts toward the owner moving left.

View diagram Hide diagram

Scroll horizontally to explore

Owner/contractor payment structures plotted on a cost-overrun-risk spectrum A horizontal risk axis whose two arrowheads carry the captions that name them: the left arrowhead points at owner bears overrun, the right arrowhead at contractor bears overrun. Cost-plus-fee sits at the owner end, GMP just past it with its dot and name highlighted (cost-plus with a cap), unit price in a shared zone where quantity drives the total, and stipulated sum at the contractor end as a fixed lump-sum price. owner bears overrun contractor bears overrun Cost-plus-feepay actual cost + fee GMPcost-plus with a cap Unit priceshared — quantity varies Stipulated sumfixed lump-sum price

A GMP (guaranteed maximum price) caps the owner’s exposure, and unit-price risk is shared because the quantity varies.

Confusions / comparison

Payment basisWho bears overrun riskCost certainty for ownerWhen used
Stipulated sumContractorHigh — fixed priceFully designed project, competitive bid
Cost-plus-feeOwnerLow — open-endedIll-defined scope; high owner trust
GMP (cost-plus with cap)Owner up to cap; contractor above capMedium — ceiling known, actual costs varyCMc delivery; phased or fast-track projects
Unit priceShared — quantity unknownPartial — price/unit fixed, total variesEarthwork, piling, work of unknown quantity

→ pp-architect-compensation-methods (this module): the parallel owner-architect fee structures · pp-fast-track-scheduling (this module): fast-track projects commonly use GMP + CMc delivery · ProPractice — AIA A101 / A133: the AIA document pair for each payment structure.