← Project Management

Sheet G-116
PjM PcMCE

Dispute Resolutionconcept

Termination and suspension: for cause, for convenience, and suspension compared

One-line orientation

Three ways a contract can end early — for cause (breach), for convenience (owner’s right, no fault), or temporarily by suspension — each with different triggers and compensation consequences; the cause-vs-convenience distinction is the most-tested trap.

Key points

  • Termination for cause (default):
    • Triggered by a material breach — persistent failure to perform, abandonment, non-payment, or other default by the breaching party.
    • A material default may give the other party a right to terminate for cause after required notice and any opportunity to cure.
    • Under A201 Art. 14: the contractor may terminate for prolonged work stoppage or owner non-payment; the owner may terminate the contractor for repeated failure to perform or abandonment.
    • The breaching party’s compensation rights are reduced or eliminated.
  • Termination for convenience:
    • The owner’s right to end the contract without cause — no breach required, no fault assigned.
    • The terminated party is generally paid for earned work. The agreement controls wind-down costs and any separate termination fee.
    • This is a pure business decision by the owner; the other party cannot block it.
  • Suspension:
    • A temporary pause rather than an end to the contract.
    • Owner-initiated suspension (B101 Art. 9): Owner may suspend the architect’s services with payment for work performed. If suspension exceeds 90 days, the architect may terminate the agreement.
    • Architect-initiated suspension for non-payment (B101 Art. 9): The architect may suspend services after giving the owner notice of non-payment. On resumption, the architect’s compensation and schedule are adjusted to reflect startup costs and the period of delay.
    • Under A201, the contractor may also stop work for prolonged owner non-payment before escalating to termination.

Three exit paths: for cause · for convenience · suspension

SCHEMATIC · NOT TO SCALE

Each path has a different trigger, a different party who may invoke it, and a different compensation consequence.

View diagram Hide diagram

Scroll horizontally to explore

Three contract exit paths: termination for cause, termination for convenience, and suspension Three project-timeline rows compare termination for cause, termination for convenience, and suspension. For cause follows a material breach and the contract’s notice and cure requirements. For convenience requires no fault and is shown as the owner’s contractual right; earned work is generally paid, while the agreement controls wind-down costs and any separate termination fee. Suspension is a temporary pause that may resume with an adjusted fee and schedule; an owner pause over 90 days may let the architect terminate under B101. TERMINATIONSFor causebreachtriggermaterial breachwho may acteither partycompensationbreaching party’s recovery is cutFor convenienceclean endtriggerno fault requiredwho may actowner onlycompensationearned work paid · agreement controls other costsSuspensionresumestriggertemporary pausewho may actowner, or the architect after non-payment noticecompensationresumes with adjusted fee + scheduleescalationan owner pause over 90 days lets the architect terminate

For cause = breach; for convenience = no fault. The agreement controls earned payment, wind-down costs, and any termination fee.

Shown: the AIA termination and suspension provisions — B101 Art. 9 and A201 Art. 14. Suspension is not owner-only: after notice of non-payment the architect may suspend its services.

Confusions / comparison

Termination for causeTermination for convenienceSuspension
TriggerMaterial breach / defaultOwner’s election, no fault requiredTemporary stoppage (non-payment or owner’s decision)
Who can invokeEither party (against the defaulting party)Owner onlyOwner (B101); architect for non-payment (B101); contractor for non-payment (A201)
Compensation effectDepends on the default and contract remediesEarned work is generally paid; agreement controls wind-down costs and any termination feeResumed with adjusted fee and schedule; architect may terminate if owner’s suspension exceeds 90 days
AIA article referenceA201 Art. 14 / B101 Art. 9A201 Art. 14 / B101 Art. 9B101 Art. 9 / A201 Art. 14

→ pp-dispute-resolution-ladder (this module): the dispute escalation path when a party does not terminate but disputes a claim · pp-mediation-vs-arbitration-vs-litigation (this module): the binding resolution methods · ProPractice: AIA B101 Art. 9 and A201 Art. 14.

Spotted an issue with this card? Tell us →

Related units