Construction Administrationconcept
Payment certification: Schedule of Values, G702/G703, and the architect's role
One-line orientation
The contractor’s monthly pay application — built on a Schedule of Values and submitted on G702/G703 — triggers the architect’s certification role, and the standard of that certification (a representation, not a guarantee) is a heavily tested boundary.
Key points
- Schedule of Values: The contractor subdivides the contract sum into line items corresponding to work scopes (e.g., concrete, framing, mechanical rough-in). Submitted early in construction and approved by the architect. All subsequent pay applications draw from it.
- Application for Payment (G702/G703): Each payment period, the contractor submits a pay application stating the percentage of each line item completed and the dollar amount earned. G703 is the continuation sheet showing the line-by-line breakdown; G702 is the summary and certification page. The contractor certifies that the work represented is accurate.
- Architect’s review and certification: The architect reviews the application against site observations and issues a Certificate for Payment on G702 for the amount certified. The standard of care language: certification is made “to the best of the architect’s knowledge, information, and belief” — it is a representation, not a guarantee that work is defect-free or fully in conformance.
- Retainage: A percentage withheld from each progress payment to provide the owner leverage for completion. It is commonly around 10% in practice, but AIA forms track the retainage selected by the parties rather than imposing a universal default. The contract and applicable law control when retainage is reduced or released; do not assume Substantial Completion automatically releases it.
- Current AIA form years: G702 and G703 remain listed by AIA as 1992 forms.
Confusions / comparison
| Schedule of Values | Application for Payment | Certificate for Payment | |
|---|---|---|---|
| What it is | Breakdown of contract sum into line items | Contractor’s monthly request for payment based on percentage complete | Architect’s written certification of amount due |
| Who produces it | Contractor (approved by architect) | Contractor | Architect (signed on G702) |
| Timing | Submitted at construction start | Submitted each payment period | Issued after architect reviews pay app |
| AIA form | Part of G703 | G702 + G703 | G702 (architect’s signature block) |
| Standard | N/A | Contractor certifies accuracy | Architect certifies “to knowledge, information, and belief” — representation only |
Related
→ pp-substantial-vs-final-completion (this module): the milestone events that trigger retainage release and final payment · pp-change-order-vs-ccd (this module): how approved change orders update the contract sum tracked on pay applications · pp-architect-site-observation-duties (this module): architect’s site visits that inform the pay application review.
Spotted an issue with this card? Tell us →