Scheduling methods: bar chart / Gantt, CPM, milestone chart compared

One-line orientation

Scheduling tools differ in whether they show task dependencies and the critical path — CPM is the exam-relevant method because it identifies exactly which activities control the project completion date.

Key points

  • Bar chart / Gantt chart:
    • Tasks listed vertically, time horizontally; each task shown as a bar.
    • Shows what is happening at any point in time and the sequence of tasks.
    • Easy to create, easy to read; suitable for projects of any size.
    • A plain Gantt chart does not show task dependencies or the critical path. Modern scheduling software may add dependency links to a Gantt display.
  • Milestone chart:
    • Plots only key milestone events (phase completions, permit dates, owner approvals) on a timeline.
    • No task bars or logic; suitable for short projects with few tasks or for executive-level reporting.
  • Critical Path Method (CPM):
    • The Critical Path Method (CPM) links tasks by their dependencies, then shows which sequence controls the earliest completion date.
    • Each task is represented by an arrow (solid); numbered circles mark the beginning and ending points of each activity.
    • A task cannot start until all tasks leading into its start node are complete.
    • Dependency: a relationship where one task must finish before another can start.
    • Critical Path: the longest sequence of dependent activities from start to finish. The sum of durations on this path equals the minimum project duration.
    • Float (slack): the amount of time a non-critical activity can slip without delaying the project. Critical-path activities have zero float.
    • Dummies: dashed arrows showing dependency relationships only — no duration, no work. Used in arrow-diagramming method networks to preserve unique activity numbering.
    • Delays to any critical-path task delay the project; delays to non-critical tasks may not (as long as they stay within their float).
    • Essential for CMc delivery and fast-track projects; typically software-generated on large jobs.

Gantt timing vs CPM (critical path method) topology

The same schematic nine-day schedule: neutral bars above, dependency arrows below

View diagram Hide diagram

Scroll horizontally to explore

A Gantt bar chart compared with a CPM dependency network The upper lane is a four-row task-by-day Gantt chart. Tasks A through D appear as neutral horizontal bars on one numbered time axis, with no dependency connectors or critical highlighting. The lower lane is a numbered-node CPM network. The continuous blue route from node 1 through nodes 2 and 3 to node 5 contains A for three days, B for four days, and D for two days, totaling nine days and directly labeled as the critical path with zero float. A neutral curved branch from node 2 is activity C for four days, ending at its own node 4 and paired with a bracket labeled two days float. From node 4 a dashed arrow labeled dummy, zero days, runs into the finish node 5; unlike every other arrow in the network it carries no work and no duration, only the logical dependency. GANTT · DURATION AGAINST TIMEbars show when + how long0379DAYTask A3dTask B4dTask C4dTask D2dCPM (CRITICAL PATH METHOD) · DEPENDENCY TOPOLOGYarrows show what must precede whatCritical path · zero floatA · 3 daysB · 4 daysD · 2 daysC · 4 days · non-criticalDummy · 0 daysavailable float2 days12345

A plain Gantt chart does not prove dependencies or identify the critical path.

A dummy carries a logical dependency only — no duration, no work — so each activity keeps unique node numbers.

Confusions / comparison

Bar chart / GanttCPM networkMilestone chart
Shows dependencies / logic?NoYesNo
Shows critical path / float?NoYesNo
Level of complexitySimpleDetailedMinimal
Best forAny project; easy communicationLarge, complex projects; fast-track / CMcShort projects; executive summaries

→ pp-fast-track-scheduling (this module): fast-track projects require CPM to manage overlapping design and construction packages · pp-construction-payment-basis (this module): CMc/GMP delivery commonly uses CPM · ProPractice — work plan and fee monitoring: design schedules are commonly shown as Gantt charts; CPM is for construction.