AIA G-series administrative forms: G701, G702, G703, G704, G710, G714, G716

One-line orientation

G-series forms document payments, changes, questions, and completion milestones during construction. Learn what action triggers each form and who prepares or signs it.

Key points

  • Payment forms:

    • G702 — Application and Certificate for Payment: The contractor submits an application stating the percentage of work complete and value of stored materials. The architect reviews (often coordinated with site visits) and, if reasonable, issues a certificate for payment. Contractor certifies conformance; architect’s certification is based on the architect’s knowledge, information, and belief.
    • G703 — Continuation Sheet: The schedule-of-values itemization that accompanies G702. Shows the breakdown of the contract sum by work category, amounts previously certified, and amounts requested in the current application.
  • Substantial Completion:

    • G704 — Certificate of Substantial Completion: Documents the date the work is sufficiently complete for the owner’s intended use. The architect issues it; owner and contractor also sign. Nonconforming work is listed as exceptions. A project may have multiple G704s for separate portions of work. Starts warranty/guarantee periods and may trigger retainage reduction/release as the contract permits.
  • Changes in the work (from no change in cost or time to an unresolved adjustment):

    • G710 — Architect’s Supplemental Instructions (ASI): For minor changes that do not affect contract sum or contract time. The architect issues unilaterally. If the contractor agrees the change is truly minor, the work is done without adjusting money or schedule.
    • G701 — Change Order: Used when a change does affect cost and/or schedule and all three parties (owner, contractor, architect) agree on the adjustment. All three sign. Money changes hands and/or the schedule shifts.
    • G714 — Construction Change Directive (CCD): Issued when the owner and contractor cannot agree on the cost or time impact of a required change. The architect directs the contractor to proceed while the dispute is resolved — either by converting the CCD into a G701 Change Order or escalating to mediation/arbitration.
  • Information requests:

    • G716 — Request for Information (RFI): The contractor typically submits this when the contract documents are unclear or insufficient. The architect responds. Large projects can generate over 1,000 RFIs. The architect’s response dictates which next form is needed: G710, G701, or G714.

AIA change workflow: from RFI to the right change form

An RFI (G716) routes the architect’s response to one of three change forms.

View diagram Hide diagram

Scroll horizontally to explore

AIA G-series change workflow from RFI to the appropriate change form A decision tree. The contractor issues a G716 RFI when the contract documents are unclear; the architect responds (highlighted pivot) and the response routes to one of three forms. If the change is minor with no cost or time impact: G710 ASI, issued by the architect alone; an amber caution under that branch warns that accepting the ASI without objection forfeits a later cost or time claim. If the change has an agreed cost or time adjustment: G701 Change Order, signed by owner, contractor, and architect. If the cost or time is disputed: G714 Construction Change Directive, by which the architect directs the work to proceed, later resolved into a G701 or escalated to mediation. A footnote notes the separate payment and completion forms: G702 application for payment, G703 continuation sheet, and G704 certificate of substantial completion. G716 · RFIcontractor: docs unclearArchitect responds→ which form?G710 · ASIminor — no cost/timearchitect aloneG701 · Change Ordercost/time agreedO + C + A all signG714 · CCDcost/time disputedowner + architect directAccepting the ASI without objectionforfeits a later cost/time claim→ resolve to G701, or escalate to mediation

Separate (not changes): G702 pay application + G703 continuation sheet · G704 substantial completion (sets warranty start). G702, G703 and G704 cover payment and completion rather than change.

Confusions / comparison

FormFull namePurposeWho issues / who signs
G701-2017Change OrderFormal change with agreed cost / time adjustmentArchitect prepares; owner + contractor + architect all sign
G702-1992Application and Certificate for PaymentMonthly payment request + certificationContractor submits application; architect issues certificate
G703-1992Continuation SheetSchedule-of-values breakdown accompanying G702Contractor prepares; submitted with G702
G704-2017Certificate of Substantial CompletionCertifies work is ready for owner’s use; sets warranty start and may affect retainageArchitect issues; owner + contractor sign
G710-2017Architect’s Supplemental Instructions (ASI)Minor change — no cost or schedule impactArchitect issues unilaterally
G714-2017Construction Change Directive (CCD)Disputed change — architect directs work to proceed while cost is unresolvedArchitect (on behalf of owner) issues; owner + architect sign; contractor must comply
G716-2004Request for Information (RFI)Clarification request about contract documentsContractor typically initiates; architect responds

→ AIA owner-contractor documents (this module): A201 General Conditions governs when and how these G-forms are used · AIA documents by delivery method (this module): which delivery methods use these standard G-forms · Construction administration responsibilities (same topic): architect’s role in certifying payments and issuing change directives.