Contract modifications: Change Order, Construction Change Directive, and Minor Change compared

One-line orientation

Three mechanisms exist to modify an A201-based construction contract — Change Order, Construction Change Directive, and Minor Change — and they are tested because each differs in who signs, whether agreement is required, and what can change.

Key points

  • Change Order (CO): A formal written amendment signed by owner + contractor + architect. Adjusts the contract sum and/or contract time. Used when all three parties agree on the scope, cost, and time impact before the work proceeds. Most common mechanism for scope changes.
  • Construction Change Directive (CCD): Signed by owner + architect only. Directs the contractor to proceed with a change before owner and contractor have agreed on cost/time. Work does not wait for negotiation; adjustment is resolved later (by agreement → then CO, or by method in contract). The contractor is bound to proceed.
  • Minor Change / Architect’s Supplemental Instruction (ASI): Issued by the architect alone. Must cause no change to contract sum or contract time. Used for clarifications, field corrections, and minor adjustments consistent with design intent.

Contract modifications: who signs decides which document

Who signs is the trap: a Change Order needs all three, a CCD needs owner and architect, a Minor Change / ASI is architect-only.

View diagram Hide diagram 3 panels

3 panels side by side — swipe to compare

Change Order vs Construction Change Directive vs Minor Change by signer and effect Three columns comparing the A201 contract-modification documents, all three of which fall under A201 Article 7, Changes in the Work. A Change Order is signed by all three parties — owner, contractor, and architect (all three signer chips highlighted) — changes the contract sum and time by agreement reached up front. A Construction Change Directive is signed by owner and architect only (the contractor chip is open/dashed) — it directs work to proceed before cost and time are agreed, with the adjustment resolved later. A Minor Change or ASI is signed by the architect alone — it makes no change to contract sum or time and covers clarifications only. Who signs is the primary distinction; a gradient bar beneath runs from all-three-sign with sum and time changes down to architect-only with no change. Change Order (CO)who signs:OCAchanges sum / time?Yes (agreed up front)all 3 agree on cost/time before workConstruction Change Dir.who signs:OCAchanges sum / time?Maybe — resolved laterwork must proceed;cost/time not yet agreedMinor Change / ASIwho signs:OCAchanges sum / time?Noclarification only —no cost or timeall three sign · changes sum / timearchitect only · no change
  • filled = signs (O owner · C contractor · A architect)
  • open = does not sign (CCD omits the contractor; ASI is architect-only)

All three mechanisms live under A201 Article 7 — Changes in the Work.

Confusions / comparison

Change Order (CO)Construction Change Directive (CCD)Minor Change / ASI
Who signsOwner + Contractor + ArchitectOwner + Architect (contractor NOT required)Architect alone
Changes contract sum?Yes (agreed amount)Possibly — amount resolved laterNo
Changes contract time?Yes (agreed extension)Possibly — resolved laterNo
When usedAll parties agree on cost/time before proceedingWork must proceed; cost/time not yet agreedClarification; no cost or time impact
A201 articleArticle 7Article 7Article 7

→ pp-submittals-and-rfis (this module): how the architect handles contractor-initiated information requests during CA · pp-architect-site-observation-duties (this module): architect’s authority to reject nonconforming work, which may trigger a CCD or CO · pp-payment-certification-g702 (this module): how approved Change Orders roll into the updated contract sum on pay applications.