Structureconcept

Structural system selection by material

One-line orientation

Choosing a structural system is a match between required span/height and the material that delivers it economically — the exam tests whether you can pair a program to the right system.

Key points

  • Light wood frame — common for single-family and low-rise residential or commercial work. Small members simplify MEP routing; members are often spaced at 16 or 24 inches on center, and I-joists or trusses extend spans. Wood is combustible, but tested assemblies can still achieve a fire-resistance rating. Height and area limits depend on the complete construction type.
  • Heavy / mass timber — mid- to high-rise; larger members with better fire resistance. Solid beams/girders 4–12” thick to ~32 ft; glulam 3–75” deep to ~65 ft; CLT 3–12” thick to ~60 ft lengths.
  • Load-bearing masonry — primarily wall construction, with floors and roofs carried by other systems. CMU is generally faster and more economical than brick. A cavity wall commonly uses a structural backup, a drained air space, and a nonstructural veneer tied to the backup.
  • Cast-in-place (site-cast) concrete — columns, walls, beams, slabs. Needs formwork + curing; post-tensioning adds strength/span. Columns min. ~10” square / 12” round; beams/girders to ~90–100 ft; slabs ~30 ft (one-way) to ~100 ft (two-way post-tensioned).
  • Precast concrete — fast-track, pre-stressed/pre-cured; shallower spanning members; economical on uniform grids. Beams/girders (rect., T, L) to ~75 ft; double-tees to ~90 ft, single-tees to ~110 ft; columns use corbels to support beams.
  • Structural steel:
    • Fire behavior: cold-formed steel is noncombustible, but members alone do not create a fire-rated assembly; hot-rolled steel often needs protection.
    • Common column shapes: W and HSS.
    • Preliminary spans: beams/girders 25–40 ft; open-web joists about 90 ft for floors and 140 ft for roofs.

Structural systems — compare members on one span scale

Every row uses the same 0–140 ft scale; gray bands are stated ranges, while labeled dots are single maximum spans.

View diagram Hide diagram

Scroll horizontally to explore

Structural systems compared by economical clear span on one ruler Four measured rows share a zero-to-140-foot ruler. Structural steel reaches 140 feet with roof open-web joists, with beams at 25 to 40 feet and floor open-web joists at 90 feet. Precast concrete marks girders at 75 feet, double-tees at 90 feet, and single-tees at 110 feet. Cast-in-place concrete marks one-way slabs at 30 feet, beams and girders at 90 to 100 feet, and two-way post-tensioned slabs at 100 feet. Mass timber marks solid beams at 32 feet, CLT at 60 feet, and glulam at 65 feet. A separate unmeasured band keeps light wood frame and load-bearing masonry off the span ranking. CLEAR SPAN · FT0255075100125140Structural steelbeams · 25–40 ftfloor OWSJ · 90 ftroof OWSJ140 ftPrecast concretegirders · 75 ftdouble-tee · 90 ftsingle-tee · 110 ftCast-in-placeone-way slab · 30 ftbeams · 90–100 ft2-way PT slab · 100 ftMass timbersolid beam · 32 ftCLT · 60 ftglulam · 65 ftCHOOSE BY SCALE / WALL LOGIC — NOT BY THIS SPAN RANKINGLight wood frameLOW-RISE SCALETrusses and I-joists extend reach; height/area limits govern.Load-bearing masonryWALL / HEIGHTWalls carry; floors and roofs use another spanning system.
  • blue band = longest reach
  • gray band = stated span range
  • dot = stated maximum

Trap: light wood frame and load-bearing masonry are not losing a span race; select them by low-rise scale or wall/height logic.

Confusions / comparison

SystemTypical economical spanHeight / scale fitNotes
Light wood frameMembers 16”/24” o.c.; trusses/I-joists for longer spansLow-riseCombustible; rated assemblies are possible; height/area depend on construction type
Heavy / mass timberGlulam ~65 ft · CLT ~60 ft · beams ~32 ftMid- to high-riseBetter fire resistance than light frame
Load-bearing masonryWalls (spanning via other systems)Brick to ~20 storiesCavity wall = CMU + air space + veneer
Cast-in-place concreteBeams ~90–100 ft · slabs 30–100 ftAnyFormwork + curing; post-tension for span
Precast concreteBeams ~75 ft · double-tee ~90 ft · single-tee ~110 ftFast-track, uniform gridsPre-cured; shallower members
Structural steelBeams 25–40 ft · open-web joist 90 ft (floor) / 140 ft (roof)Any, incl. long-spanHot-rolled needs fire protection

→ Column buckling & K-values (this topic): why steel HSS/W columns resist buckling · End connections (this topic): how the system’s joints behave · Enclosure control layers (Enclosure): how the chosen structure carries the cladding.